Reconstruction of two railway bridges on railway line no 47

In progress

Reconstruction of two railway bridges on railway line no 47

Design documentation for two railway bridges at km 22.991 and at km 24.205 of the electrified railway line No. 47 WKD into a frame culvert made of reinforced concrete with accompanying infrastructure.

Property Summary

Project documentation including: Preliminary Design, Building Permit Documentation, building permit, Detailed Design , Technical Specifications, investor's cost estimate.

Disciplines: bridges, railway track and p-way, roads, network and sanitary installations, project management and technical coordination.

Property Features

  • Address: Reguły near Warsaw
  • Project duration: June 2023-June 2024
  • Client: WKD
  • Investor: Warszawska Kolej Dojazdowa (WKD)